Search This Blog

Saturday, December 17, 2011

Three Gorges Dam: China


World Records Set by the Three Gorges Dam


The world’s largest and grandest water conservancy project, the Three Gorges Dam has set a series (over 100) of
world engineering records by various indices. It is, or has:-

- the world’s most effective multi-functional water control system, consisting of a dam, a five-tier ship lock, and 26 hydropower turbo-generators;
- the world’s largest power station, total installed capacity reaching 18.2 million kW and annual power generation 846.7 billion kWh;
- the world’s grandest engineering project for water conservancy, earthwork (excavation & backfilling) totaling 134 million m3, concrete consumption 279.4 million m3, steel reinforcement 463,000 tonnes;
- the world’s greatest floor discharging capacity, up to 102.5 m3/s;
- the world’s largest number of stages of ship locks (staircase locks, nos. two, each with five stages and a total water head of 113m);
- (yet to be completed) the world’s largest ship lift (dimension of the basin: 120×18×3.5m), maximum vertical travel distance being 113m, capable of lifting ships of 3000t;
- the world’s largest human resettlement program associated with an engineering project, total population having to be relocated being estimated at 1.13 million.

Friday, December 16, 2011

Marcellus Cumulative Gas Production West Virginia

Marcellus Shale
Comingled wells excluded
259 Total wells
212 Vertical, 47 horizontal

Marcellus Shale West Virgina


The Middle Devonian Marcellus Shale Play has put the Appalachian Basin at the center of a national debate concerning America’s future energy supply. Although it has been received in the region with mixed reviews, this highly organic shale formation has secured itself as a major contributor to the natural gas supply of West Virginia and other states in the Basin. As production continues throughout West Virginia, areas of high production continue to emerge; however, it appears that some of these “sweet spots” may not actually be within the “Marcellus” per se, but rather, in other, overlying Devonian shales.


Sunday, December 4, 2011

Time for Energy Secretary Chu to Leave?

The White House has denied the critics charges of any connection between politics and "green energy" loans, however, recent emails and scrutiny at the Solyndra Congressional Inquiry have discovered a preference  given to Democrat donors seeking loans. The emails suggest a correlation beyond just the timing timing of political announcements to questions about the White Houses overall policy of handing out taxpayer money.

The Solyndra hearing revealed a series of questionable actions, 1)the rush to announce the Solyndra loan and 2) the process that lacked appropriate financial oversight. Solyndra investor George Kaiser and other Obama contributors had "unfettered" access to the West Wing of the White House. Additionally, Energy Secretary Chu approved subordination of the Solyndra loans so that taxpayers would be repaid after two commercial firms, a violation of the Energy Policy Act of 2005.

The green energy subsidies show that several well connected Democrats obtained taxpayer assistance for environmentally friendly projects. These recipients include: (from Fox news)

-- Solyndra, which received $535 million in loan guarantees and whose chief investor was the George Kaiser Family Foundation. George Kaiser was an Obama campaign bundler.

-- Brightsource Energy, which received $1.6 billion and whose senior adviser is Robert Kennedy, Jr., an early Obama backer;

-- Solar Reserve, which got a $737 million loan, and whose major investor is a company run by Michael Froman, who was a deputy assistant to the president. Froman bundled up to $500,000 for the president's 2008 campaign;

-- Granite Reliable Wind Generation, which received a $168.9 million loan. The company's majority owner is a firm formerly led by Nancy Ann DeParle, now a White House deputy chief of staff and former head of the president's health care communications team during the reform debate; and

-- Abound Solar, which received a loan guarantee worth $400 million. A key investor is billionaire heiress Pat Stryker, who gave $87,000 to Obama's inauguration committee, and hundreds of thousands more to Democratic causes.

Read more: http://www.foxnews.com/politics/2011/11/16/solyndra-case-reveals-gateway-between-administration-loans-obama-allies/#ixzz1fUqe7CB0

Peter Schweizer, author of "Throw Them All Out", wrote that at least 10 members of Obama's finance committee and more than a dozen of his campaign bundlers took money from administration loan programs.

Secretary Chu approved the Solyndra loan in September 2009. The braniac Nobel prize winner in Physics, testified that he was "not aware" of staffers predictions that Solyndra would go broke and run out of cash by September 2011. He clearly missed the the Office of Management and Budget recommendation that the deal be "notched down". At Solyndra's groundbreaking he announced, "If you build a better solar panel, the world will beat a path to your door."

In March 2010, PricewaterhouseCooppers warned that Solyndra's recurring losses and negative cash flows" raise a substantial doubt about it's ability to continue as a going concern". Chu remained a booster for the project. In May 2010, President Obama appeared at a Solyndra event and proclaimed," the true engine of economic growth will always be companies like Solyndra."

By October, Solyndra CEO Brain Harrison informed the DOE that the company was about to lay off workers. The company shut one of its plants and laid off 40 workers the day after the November elections.
Secretary Chu admits he approved a  to put $75 million into Solyndra which included a sweetener that put investors ahead of taxpayers in the payback line that follows bankruptcy. This gambit failed and Solyndra laid off 1,000 workers.

The Nobel prize winner's pet pick was a bust. No scandal? In February 2009, the former Solyndra CEO Chris Gonet set 10 conditions for the Administration to meet to help Solyndra raise an additional $147 million.

No.9. "Fundraising suppport after conditional commitment: Steven Chu visits Solyndra with press interviews (target by end of March)."

Solyndra Scandal key Players

Saturday, December 3, 2011

Methane Hydrates World Map


Methane hydrates occur in polar permafrost regions and marine outer continental margins and represent a potentially enormous energy resource.
Hydrates are naturally occurring crystalline compounds of natural gas enclosed within a cage-like lattice of water ice. Chemists call such structures clathrates. In methane hydrates, water crystallizes in the cubic system, rather than in the hexagonal structure of normal ice. The resulting compound packs a lot of methane in its dense organization. One cubic foot of hydrate contains about 164 cubic feet of methane gas.

With adequate gas concentrations, methane hydrates form and are stable under moderate- to high pressure, low temperature conditions. This Methane Hydrate Stability Zone (MHSZ) typically occurs: 1) on continental margins at water depths greater than about 300 m and bottom water temperatures close to 0° C, where gas hydrate is found from the sediment surface to depths of about
1100 m below the seafloor, and 2) in polar continental regions, where gas hydrate can be present in sediment and permafrost at depths between about 150 and 2000 m.

Early estimates of the total resource were as speculative as they were impressive. Current work using geology-based Total Petroleum System (TPS) assessments still yields very large numbers.

The USGS recently estimated that there are about 85.4 trillion cubic feet (Tcf) of undiscovered, technically recoverable gas resources within methane hydrates in northern Alaska alone (Collett, 2009). The Minerals Management service conducted an evaluation of the petroleum system for the Gulf of Mexico and estimated a mean value of 21,444 Tcf with 6,717 Tcf in place in sandstone reservoirs

(Frye, 2008). Mean estimated resource of domestic methane hydrate in place is about 200,000 Tcf (NETL, site accessed 4/28/11).


Source

Two primary source mechanisms have been recognized based on carbon and hydrogen isotopic analysis (Uchida, et al, 2009): microbial decay of organic matter within the gas-hydrate stability zone and thermogenic methane. Thermogenic methane may migrate from thermally mature, deep-seated organic shales, or by leakage from deeper, conventional free gas reservoirs (Lorenson, 2011).

Reservoir

An important difference between methane hydrate accumulations and more conventional gas fields is the nature of the reservoir beds containing the gas: methane hydrate deposits occur in young, relatively unconsolidated sediments where the ice-like hydrate structure holds the gas in place. Methane hydrates occur within a range of reservoir facies, from mudstones to gravels. Sandy siliciclastic reservoirs are considered to be the most favorable for commercial exploitation.

Seal

The seal is provided by the clathrate structure itself. In fact, it is increasingly recognized that the hydrate accumulations may provide a top and lateral seal for deeper free-gas reservoirs outside the methane hydrate stability zone (MHSZ).

Trap

The trapping mechanism, too, is attributed to the arrangement of methane within the clathrate structure. As free gas migrates into the MHSZ, it is chemically trapped within the crystalline configuration of the naturally formed clathrate.
( from Search & Discovery #80193)

Friday, December 2, 2011

Anadarko 's Mozambique 10 TFC Discovery



• Barquentine-2 was drilled to a total depth of 13,500 feet in Offshore

Area 1 (APC WI 36.5%) of the Rovuma Basin in a water depth of

approximately 5,400 feet. The well encountered more than 230 net feet

of high-quality gas sand in static communication with the Barquentine-1

well, located 2 miles to the northwest. The entire reservoir section was

cored and will be used to help optimize the development plan for the

area. The Barquentine-2 wellbore has been temporarily abandoned and

will be used in a testing program in early 2012.



• Subsequent to quarter end, Anadarko announced the results of the

CamarĂ£o-1 well. The appraisal section of the well encountered

approximately 240 net feet of natural gas pay in an excellent-quality

reservoir and confirmed static pressure connectivity with previously

announced discoveries at Windjammer and Lagosta. The well also

discovered approximately 140 net feet of natural gas pay in shallower

Miocene and Oligocene sand packages. The well was drilled to a total

depth of 12,630 feet in water depths of approximately 4,730 feet. The

CamarĂ£o well has been saved and will be used in the upcoming DST

program.



• Based upon the five successful penetrations in the complex to

date, the confirmed static pressure connectivity and the numerous

cores that have been analyzed, the company has a high level

of confidence that the Windjammer, Barquentine and Lagosta

complex holds in excess of 10 trillion cubic feet of recoverable

natural gas resources. Given the increased recoverable resource

base potential of this complex, initial development plans have

been expanded to a minimum of two 5-million-tonne-per-annum

LNG trains with the flexibility to develop additional trains based

upon continued exploration and appraisal success. Once the

first two trains are constructed, this infrastructure is expected

to provide economies of scale that can significantly reduce

expansion costs for additional trains.



• The Barquentine-3 appraisal well is currently being drilled and

the rig will continue to drill appraisal wells through the end of

2011. The company is in the process of mobilizing a second rig

to Mozambique late in 2011 to conduct an extensive reservoir

testing program and up to seven exploration/appraisal wells

during the next 12 months.